Yongninghui Project – Self-Balanced Pile Load Testing, Xuyong County, Luzhou
Release time:
2025-09-29 10:01
Project Overview
Project Name: Yongninghui Project – Self-Balanced Testing
Project Type: Building Construction
Location: Near Shengshi Huadu Bus Station, Xuyong County, Luzhou City, China
Testing Equipment: RSM-JC6(C) Static Load Tester
Testing Purpose & Method
The primary objective of the inspection was to verify the bearing capacity of building foundation piles. The self-balanced method was employed, a reliable approach that allows for pile load testing without the need for large reaction structures, making it suitable for dense construction sites.
Testing Scope
Random sampling inspection of building foundation piles
Measurement of ultimate bearing capacity and pile displacement behavior under load
Testing Results
Findings: All tested piles achieved the required bearing capacity and demonstrated minimal displacement under load.
Issues Detected: None
Impact: No negative effects observed; results confirmed compliance with design standards.
Evaluation
Engineering Evaluation: The pile foundations fully met safety and quality requirements, providing assurance of long-term structural stability.
Equipment Performance: The RSM-JC6(C) static load tester proved effective and reliable, meeting all on-site testing needs with precise data acquisition.