Baiquan Substation Project – Static Load Pile Testing

Release time:

2025-09-29 09:51

Project Overview

Project Name: Baiquan Substation Project

Project Type: Pile Foundation Testing

Location: Dongxihu District, Wuhan, China

Testing Equipment: RSM-JC6 Static Load Tester

 

Testing Purpose & Method
The objective of the testing was to provide reliable load-bearing data for the reconstruction of the Baiquan Substation. The static load test method was applied, which is regarded as the most direct and authoritative approach to evaluating pile bearing capacity.

 

Testing Results

The static load tests confirmed that the pile end characteristic value of 730 kN fully satisfied the design requirements.

No abnormalities were detected during loading, and pile performance remained stable throughout the test process.

 

Evaluation

Engineering Evaluation: The results provided a solid technical basis for foundation design, confirming that the pile capacity meets the required safety margin for substation reconstruction.

Equipment Performance: The RSM-JC6 static load testing system performed reliably, offering accurate data acquisition and stable operation under field conditions.