Jinan Metro Line 7 Phase I – Civil Works Section 4-1
Release time:
2025-09-29 09:48
Project Overview
Project Name: Jinan Metro Line 7 Phase I Civil Engineering General Contract – Civil Section 4-1
Project Type: Municipal Infrastructure (Urban Rail Transit)
Location: Jinan, Shandong Province, China
Testing Equipment: RSM-HGT(D) Ultrasonic Borehole Quality Tester
Testing Purpose & Method
The objective of the inspection was construction self-checking for pile borehole quality at the Muniushan Station group pile foundation. The ultrasonic borehole testing method was adopted to assess borehole geometry, including diameter, verticality, and wall continuity.
Testing Scope
Coverage: Multiple pile boreholes at Muniushan Station
Focus: Verticality deviations, borehole diameter accuracy, and wall stability
Testing Results
Key Finding: Borehole #86 showed a verticality deviation greater than 1%, exceeding design tolerance.
Follow-Up Action: The construction team immediately carried out overnight remediation, after which a re-test confirmed that verticality had been corrected.
General Outcome: Other boreholes met quality standards, with no major issues detected.
Evaluation
Engineering Evaluation: Overall borehole quality was good, with the remediation ensuring compliance across all tested piles.
Equipment Performance: The RSM-HGT(D) provided highly practical performance, delivering clear and precise wall signals, which greatly facilitated on-site quality control.